On May 17, 2020, about 0530 local time, a shipyard worker reported that the towing vessel Alton St. Amant was partially submerged while moored at a shipyard in the Harvey Canal in New Orleans, Louisiana. There were no crewmembers or shipyard workers aboard the vessel. Approximately five gallons of diesel fuel were released into the water. Damage to the vessel was estimated at $1.5 million. No injuries were reported.
The probable cause of the flooding of the towing vessel Alton St. Amant was the absence of shipyard pre-inspection and monitoring procedures for water transfer, which resulted in potable water tanks overflowing through their open access hatches during an unmonitored transfer.
Precautions for Tank Filling
Crew and shipyard personnel designated to conduct liquid transfers must be aware of the status of a vessel's tanks, including their access hatches and associated piping systems, whether ashore or at sea. When filling a tank, open access hatches create a risk of unintended flooding. Pre-inspection and monitoring of transfers provide the opportunity to identify and remedy any issues in order to ensure they are safely completed.