Collapsed bridge center section, looking southeast.

​​​Collapsed bridge center section, looking southeast.

Collapse of I-35W Highway Bridge

What Happened

​About 6:05 p.m. central daylight time on Wednesday, August 1, 2007, the eight-lane, 1,907-foot-long I‑35W highway bridge over the Mississippi River in Minneapolis, Minnesota, experienced a catastrophic failure in the main span of the deck truss. As a result, 1,000 feet of the deck truss collapsed, with about 456 feet of the main span falling 108 feet into the 15-foot-deep river. A total of 111 vehicles were on the portion of the bridge that collapsed. Of these, 17 were recovered from the water. As a result of the bridge collapse, 13 people died, and 145 people were injured.

On the day of the collapse, roadway work was underway on the I‑35W bridge, and four of the eight travel lanes (two outside lanes northbound and two inside lanes southbound) were closed to traffic. In the early afternoon, construction equipment and construction aggregates (sand and gravel for making concrete) were delivered and positioned in the two closed inside southbound lanes. The equipment and aggregates, which were being staged for a concrete pour of the southbound lanes that was to begin about 7:00 p.m., were positioned toward the south end of the center section of the deck truss portion of the bridge and were in place by about 2:30 p.m.

About 6:05 p.m., a motion-activated surveillance video camera at the Lower St. Anthony Falls Lock and Dam, just west of the I-35W bridge, recorded a portion of the collapse sequence. The video showed the bridge center span separating from the rest of the bridge and falling into the river.

What We Found

​​We determined that the probable cause of the collapse of the I-35W bridge in Minneapolis, Minnesota, was the inadequate load capacity, due to a design error by Sverdrup & Parcel and Associates, Inc., of the gusset plates at the U10 nodes, which failed under a combination of (1) substantial increases in the weight of the bridge, which resulted from previous bridge modifications, and (2) the traffic and concentrated construction loads on the bridge on the day of the collapse. Contributing to the design error was the failure of Sverdrup & Parcel’s quality control procedures to ensure that the appropriate main truss gusset plate calculations were performed for the I-35W bridge and the inadequate design review by Federal and State transportation officials. Contributing to the accident was the generally accepted practice among Federal and State transportation officials of giving inadequate attention to gusset plates during inspections for conditions of distortion, such as bowing, and of excluding gusset plates in load rating analyses.  ​​

What We Recommended

​​We made recommendations to the Federal Highway Administration and the American Association of State Highway and Transportation Officials. One safety recommendation resulting from this investigation was issued to the Federal Highway Administration in January 2008.​ ​​

Video

I-35W Bridge Collapse Structure and Components and Initial Failure
https://youtu.be/5L6fsel9hwg?si=s-mQyxwn9xVeLSnj
 
 
 
 
 
 

​​​​​​