Safety Recommendation Details

Safety Recommendation P-80-075
Details
Synopsis: ON JANUARY 30, 1980, AN 8-INCH-DIAMETER, REFINED PETROLEUM PRODUCTS PIPELINE OWNED BY THE PIPELINES OF PUERTO RICO, INC., AND OPERATED BY THE SHELL OIL COMPANY (PUERTO RICO) LTD. WAS STRUCK AND RUPTURED BY A BULLDOZER DURING MAINTENANCE WORK ON A NEARBY WATERLINE IN THE SECTOR CANA OF BAYAMON, PUERTO RICO, ABOUT 10 MILES SOUTHWEST OF SAN JUAN. GASOLINE FROM THE RUPTURE SPRAYED DOWNHILL AND RAN OFF INTO A SMALL CREEK. ABOUT 1 1/2 HOURS LATER, THE GASOLINE VAPORS WERE IGNITED BY AN UNDETERMINED SOURCE AND EXPLODED; THE SUBSEQUENT FIRE KILLED ONE PERSON AND EXTENSIVELY DAMAGED 25 HOUSES AND OTHER PROPERTY.
Recommendation: THE NTSB RECOMMENDS THAT THE PIPELINES OF PUERTO RICO, INC.: COORDINATE WITH THE PUBLIC SERVICE COMMISSION, LOCAL FIRE DEPARTMENTS, AND OTHER UTILITIES TO DEVELOP PROCEDURES TO EMPLOY DURING PIPELINE EMERGENCIES.
Original recommendation transmittal letter: PDF
Overall Status: Closed - Unacceptable Action
Mode: Pipeline
Location: Bayamon, PR, United States
Is Reiterated: No
Is Hazmat: No
Is NPRM: No
Accident #: DCA80MP008
Accident Reports:
The Pipelines of Puerto Rico, Inc., Petroleum Products Pipeline Rupture and Fire
Report #: PAR-80-06
Accident Date: 1/30/1980
Issue Date: 2/26/1981
Date Closed: 4/13/1988
Addressee(s) and Addressee Status: Pipelines of Puerto Rico, Inc. (Closed - Unacceptable Action)
Keyword(s):

Safety Recommendation History
From: NTSB
To: Pipelines of Puerto Rico, Inc.
Date: 4/13/1988
Response:

From: Pipelines of Puerto Rico, Inc.
To: NTSB
Date: 12/7/1983
Response: IN REFERENCE TO YOUR LETTER DATED SEPTEMBER 7, 1983, WE ARE INCLUDING COPY OF OUR LETTER TO THE PUBLIC SERVICE COMMISSION DATED DECEMBER 7, 1983. [THE DECEMBER 7, 1983, LETTER FROM THE PIPELINES OF PUERTO RICO TO THE PUBLIC SERVICE COMMISSION REFERRED BRIEFLY TO A PREVIOUS LETTER DATED JULY 26, 1983. IN THE JULY 26, 1983, LETTER, THE PIPELINES OF PUERTO RICO OUTLINED THE BOARD'S RECOMMENDATIONS AND AGAIN REQUESTED THE HELP OF THE PUBLIC SERVICE COMMISSION TO IMPLEMENT THE BOARD'S RECOMMENDATIONS. THE THRUST OF THE 7/26/83 LETTER IS SUMMARIZED IN THE FOLLOWING PARAGRAPH: THE PIPELINES OF PUERTO RICO, ALTHOUGH MUCH WILLING, IS UNABLE TO IMPLEMENT THIS RECOMMENDATION WHICH REQUIRES ACTIVE PARTICIPATION OF SEVERAL PUBLIC INSTRUMENTALITIES AND AGENCIES. ONCE AGAIN WE ARE REQUESTING YOUR HELP ON THIS MATTER AND VERY RESPECTFULLY SUGGEST THAT THE PSC CALL A MEETING WITH REPRESENTATIVES OF THE CONCERNED GOVERNMENT AGENCIES WHICH AT LEAST SHOULD INCLUDE THE P.R. AQUEDUCT AND SEWAGE AUTHORITY, THE PUERTO RICO AUTHORITY OF ELECTRICAL ENERGY, THE PUERTO RICO TELEPHONE COMPANY AND THE TRANSPORTATION AND PUBLIC WORKS DEPARTMENT.

From: NTSB
To: Pipelines of Puerto Rico, Inc.
Date: 9/7/1983
Response:

From: Pipelines of Puerto Rico, Inc.
To: NTSB
Date: 7/28/1983
Response: THE PIPELINES OF PUERTO RICO (PLPR) LETTER: WE HAVE ONCE AGAIN REQUESTED THE HELP OF THE PUBLIC SERVICE COMMISSION (LETTER DATED JULY 26, 1983) TO IMPLEMENT THESE RECOMMENDATIONS, AS YOU CAN APPRECIATE THE TRIVIALITY OF PLPR TRYING TO IMPLEMENT THEM WITHOUT THE GOVERNMENT PARTICIPATION AND COMMITMENT.

From: NTSB
To: Pipelines of Puerto Rico, Inc.
Date: 5/19/1983
Response:

From: Pipelines of Puerto Rico, Inc.
To: NTSB
Date: 11/18/1982
Response: THE PIPELINES OF PUERTO RICO, INC., LETTER: IN ORDER FOR US TO COMPLY WITH RECOMMENDATION NO. 1, A LETTER WAS FORWARDED TO THE PUBLIC SERVICE COMMISSION IN WHICH WE REQUESTED THEIR COOPERATION TO IMPLEMENT ABOVE MENTIONED RECOMMENDATION. FOR YOUR INFORMATION WE ARE ENCLOSING A COPY OF OUR LETTER. TO DATE WE HAVE NOT RECEIVED RESPONSES TO OUR REQUEST FROM THE COMMISSION.

From: NTSB
To: Pipelines of Puerto Rico, Inc.
Date: 10/8/1982
Response: