Safety Recommendation Details

Safety Recommendation P-80-068
Details
Synopsis: ON JANUARY 2, 1980, CRUDE OIL LEAKED FROM A FRACTURED 22-INCH PIPELINE AT A LEVEE CROSSING AT BERWICK, LOUISIANA; THE PIPELINE IS OWNED BY THE TEXAS PIPELINE COMPANY AND RUNS BETWEEN HOUMA AND ERATH, LOUISIANA. AT 9:54 A.M., THE CRUDE OIL IGNITED. ONE PERSON WAS KILLED, ONE PERSON WAS INJURED, AND SIX HOMES WERE EITHER DESTROYED OR DAMAGED.
Recommendation: THE NTSB RECOMMENDS THAT THE TEXAS PIPELINE COMPANY: EVALUATE EXISTING PROCEDURES FOR LEAK DETECTION AND TAKE STEPS TO MAKE THESE PROCEDURES MORE EFFECTIVE.
Original recommendation transmittal letter: PDF
Overall Status: Closed - Acceptable Action
Mode: Pipeline
Location: Berwick, LA, United States
Is Reiterated: No
Is Hazmat: No
Is NPRM: No
Accident #: FTW80FP002
Accident Reports:
Report #: None
Accident Date: 1/2/1980
Issue Date: 9/24/1980
Date Closed: 5/17/1995
Addressee(s) and Addressee Status: Texas Pipeline Company (Closed - Acceptable Action)
Keyword(s):

Safety Recommendation History
From: NTSB
To: Texas Pipeline Company
Date: 5/17/1995
Response: THE BOARD NOTES THAT THE TEXAS PIPELINE COMPANY MERGED WITH TEXACO PIPELINE INC. WE ALSO UNDERSTAND THAT METERS WERE INSTALLED ON THE HOUMA, LOUISIANA, TO PORT ARTHUR, TEXAS, 22-INCH LINE, AS WELL AS OTHER PIPELINES, TO DETEST LEAKS. BASED ON THIS INFO, P-80-68 HAS BEEN CLASSIFIED "CLOSED--ACCEPTABLE ACTION."

From: Texas Pipeline Company
To: NTSB
Date: 3/15/1995
Response: WE HAVE INSTALLED METERS ON THE HOUMA TO PORT ARTHUR 22" LINE, AS WELL AS OTHER PIPELINES. THIS HAS IMPROVED OUR LEAK DETECTION CAPABILITIES.

From: NTSB
To: Texas Pipeline Company
Date: 2/11/1981
Response:

From: Texas Pipeline Company
To: NTSB
Date: 12/3/1980
Response: TEXAS PIPE LINE COMPANY LTR: THE TEXAS PIPE LINE COMPANY HAS EVALUATED ITS EXISTING PROCEDURES FOR LEAK DETECTION OF ITS MAIN LINES AND HAS FOUND SUCH PROCEDURES TO BE GENERALLY EFFECTIVE. WE ARE PLANNING TO INSTALL ADDITIONAL METERS AND ASSOCIATED EQUIPMENT ON THE HOUMA-PT. ARTHUR 22-INCH LINE TO PROVIDE A CONTINUOUS VOLUME IN - VOLUME OUT COMPARISON. THIS IS EXPECTED TO IMPROVE OUR LEAK DETECTION CAPABILITIES. OTHER PIPELINES WILL BE EVALUATED FOR POSSIBLE INSTALLATION OF A SIMILAR SYSTEM.